As of August 2018 most of the major parts have been completed, these include:
  1. Frames and Running Gear;
  2. Cylinders;
  3. Valves and Valve Gear;
  4. Footplate;
  5. Smokebox;
  6. Cab and Tanks;
  7. Bunker; and
  8. Gas Burner.
Locomotive as of August 2018


The main jobs now:

  1. Attach main components to footplate;
  2. Gas Tank;
  3. Fitting of Displacement Lubricator;
  4. Pipework;
  5. Assembling Connecting and Coupling Rods:
  6. Valve Timing;
  7. Consideration of radio control;
  8. Etc - (all I have probably forgotten).

Update:

Of course I forgot the trifling matter of painting let alone valve setting.  Doh!